Sarasota County, FL
Home MenuGovernment » Transportation » Traffic Engineering & Operations
Road & Lane Closures
Lane Closure Information: Through March 27, 2026
Siesta Dr from W Baffin Dr to Roanoke Rd
- Secor Rd from Cumberland Rd to Linden Rd
- Shamrock Dr from Sussex Rd to Queen Rd
Timings: 8 AM to 6 PM
Use caution and follow detours.
Lane Closure Information : Through March 13, 2026
Installation of FPL utility poles
- Midnight Pass Rd from Mangrove Point Rd to N View Dr
Timings: 9 PM to 5 AM
- Higel Ave from Waterside Way to Sandy Nook St
- Calle Minorga from Avenida Madera to Avenida De Paradisio
- Treasure Boat Way from Higel Ave to Featherbed Ln
- Winding Way from Winding Way to Winding Way
- Northridge Rd from Honore Ave to Sawyer Loop Rd
- On Ridgewood Rd at Hollywood Blvd
Timings: 9 AM to 4 PM
- Middlesex Pl from Bee Ridge Rd to Hina Dr
Timings: 8 AM to 5 PM
Through March 27, 2026
- Gulf Ave from N Tamiami Trl to Pine Ave
Timings: 9 AM to 4 PM
Through April 10, 2026
- Bay Rd from S Tamiami Trl to Pomegranate Pl
- S Osprey Rd from Bay Rd to Siesta Dr
Timings: 9 AM to 4 PM
Use caution and follow work zone indications and detours.
Road Closure Information : Through March 20, 2026
Arox Land Development will be closing the outer southbound lane, sidewalk, and shoulder to perform a reclaim bore access Honore Ave.
- Honore Ave from Jem Ln to Blue Water Blvd
Timings: 9 AM to 3 PM
Use caution and follow work zone indications and detours.
Lane Closure Information: From February 11, 2026 Through March 20, 2026
Installation of Force Main via boring
- Sarasota Square Blvd at S Beneva Rd to Prestancia Blvd
Timings: 7 AM to 5 PM
Use caution and follow work zone indications and detours.
Lane Closure Information: Through March 12, 2026
Traffic Management Solutions, LLC will be constructing the new signalized intersection at Laurel Road and Brahman Ave (Laurel Nokomis School). Shoulder & sidewalk closures will be required to perform directional bores and install the drill shaft foundations and underground conduits. Lane closures will be required to install and remove mast arm assemblies.
- Laurel Rd E from Twin Laurel Blvd to Old Albee Farm Rd
Timings: 8 AM to 5 PM
Use caution and follow detours.
Lane Closure Information: Removal of FPL utility poles
Through March 13, 2026
- Macheachen Blvd from Coco Ridge Cir to Warren Ridge St
- Sawyer Rd from Wilkinson Rd to Meadow Creek Dr
Removal of FPL utility poles. Timings: 9 AM to 4 PM
- On Bahia Vista St at S Brink Ave
- O n S Brink Ave at Courtland St
- On Hacienda St at S Beneva Rd
Removal of unused FPL power poles by Cadre Traffic Control, LLC. Lane and shoulder closures to be expected. Timings: 8 AM to 5 PM
Use caution and follow detours.
Lane Closure Information: Through March 13, 2026
The lane closure is for installation of the FPL underground utilities and installation of HDPE via bi-directional boring.
- S Shade Ave from Redbird Cir to Haley Ln
- Haley Ln from S Shade Ave to Riverwood Ave
- Riverwood Ave from James Ln to Haley Ln
Through March 20, 2026
Installation of FPL underground utilities via bi-directional boring work
- Briarwood Rd from Oneida Rd to Dagon Rd
- Pomelo Dr from Pine Tree Dr to Briarwood Rd
- Geneva Rd from Morningside Dr to Crocus Rd
- Crocus Rd from Geneva Rd to Dagon Rd
- Pinebrook Rd from Lucaya Ave to Ridgewood Ave
Timings: 9 AM to 4 PM
Use caution and follow detours.
Road Closure Information: Through March 12, 2026
FPL will be performing maintenance on existing utility poles. Intersection control will be done using flagging operation.
- Tuttle Ave from Bahia Vista St to Browing St
Timings: 9 AM to 4 PM
Use caution and follow detours.
Lane Closure Information: From March 3 Through March 20, 2026
Cadre Traffic Control will be removing distribution poles at various locations for an FPL project.
- Casey Key Rd from Gulf Winds Way to Casey Cove Dr
- Landfall Dr at Kingsway Dr
- Landfall Dr from Kingsway Dr to Jacana Ct
- Mission Valley Blvd from Suffolk Cir to Percheron Cir
- Percheron Cir at Palamino Cir
- Tarpon Ct at Ravenna St N
- Ravenna St S from Colonia Ln E to Florence St
Timings: 8 AM to 5 PM
Use caution and follow detours.
Lane Closure Information: Through March 27, 2026
Mastec & Tillman Fiber will be performing a directional bore to pull buried cable and install TOBY boxes and 1 vault within public right-of-way.
- Datura Rd from Terrapin Rd to W Seminole Dr
- Poppy Rd from Terrapin Rd to Bahama Rd
- Datura Rd from Drake Rd to W Seminole Dr
- W Baffin Dr from Siesta Dr to Datura Rd
MasTec will be performing a directional bore to place buried cable.
- Shamrock Rd from Yacht Club Dr to Linden Dr
- W Baffin Dr from Shamrock Dr to Secor Rd
- Sterling Rd from Devon Rd to Linden Rd
- W Baffin Dr from Sterling Rd to Roslyn Rd E
Timings: 8 AM to 5 PM
Use caution and follow detours.
Road Closure Information : March 21, 2026
W Dearborn St from Mango St to Orange St will be closed for the hosting of the Lemon Bay Sunrise Rotary Country Music Festival: Boots N Brew on March 21st.
- W Dearborn St from N Mango St to N Orange St
Timings: 7 AM to 11 PM
Use caution and follow work zone indications and detours.
Lane Closure Information : May 11, 2026
Verizon Wireless will be closing the westbound lane on Fruitville Road to perform maintenance upgrades to an existing cell pole within public right-of-way.
- Fruitville Rd from Claxtrauss Dr to East Rd
Timings: 9 PM to 5 AM
Use caution and follow work zone indications and detours.
Road Closure Information : March 11, 2026
City of Venice Intracoastal FM Project - Lane closure required for force main tie-in connection.
- E Venice Ave at Seaboard Ave
Timings: 12 AM to 12 AM
Use caution and follow work zone indications and detours.
Lane Closure Information : March 21, 2026
TLC Diversified will be performing a milling & paving operation following the installation of a 16" FM.
- Knights Trl Rd from Triple Diamond Blvd to Laurel Rd E
April 4, 2026
TLC Diversified will be performing thermopastic striping following milling & resurfacing.
- Knights Trl Rd from Triple Diamond Blvd to Laurel Rd E
Timings: 8 AM to 2 PM
Use caution and follow work zone indications and detours.
Lane Closure Information : Through April 3, 2026
Mears will be performing a natural gas install and restoration work requiring a northbound lane closure along S Shade Road at Siesta Dr.
- On S Shade Ave at Siesta Dr
Timings: 8 AM to 5 PM
Use caution and follow work zone indications and detours.
Lane Closure Information : From March 23, 2026 Through March 27, 2026
The lane closure is for maintenance tree trimming and removal
- Calle Minorga from Avenida Madera to Avenida De Paradisio
From April 6, 2026 Through April 17, 2026
- Higel Ave from Sandy Nook St to Waterside Way
- Treasure Boat Way from Higel Ave to Treasure Boat Way
Timings: 8 AM to 4 PM
Use caution and follow work zone indications and detours.
Lane Closure Information: From November 25, 2024
Honore Ave RWM Ext Phase 1. Capital Projects Honore Ave Reclaimed Water Main Project. Honore Ave from 681 to Approximately 12501 Honore Ave. From 7 AM to 7 PM
- Honore Ave from State Rd 681 to E Bay St
The public is urged to use caution around any construction activity.
Lane Closure Information:
GULF OF MEXICO DR From February 3, 2025, 1 AM to 11 PM
5 Landscaped Turn Lane medians are going to be constructed on the South End of the Key on Gulf of Mexico Dr (SR789). The Project will include widening the existing pavement width by 12 feet on the southbound side, creating a 44 feet wide pavement section. The Contractor will be Superior Asphalt and should take 180 days to complete. This is a FDOT funded project with a total project cost of $2.7 million. A notice to proceed date is pending. Charles Mopps, Town of Longboat Key, Assistant Director, 941-361-6411, ext. 2226 24/7
Lane Closure Information: From December 24, 2025 Through June 21, 2026
Soil needs to be transported from the staging area, which connects to Bahia Vista Street to the designated disposal site. This closure is necessary to ensure safety for all road users and to allow trucks to enter and exit the staging area safely. From 7 AM to 7 PM
- Bahia Vista St at Saralake Blvd
Lane Closure Information: From March 1, 2026 Through April 1, 2026
Sarasota County Capital Projects will be closing the both the eastbound and westbound lanes along Ashton Road intermittently to install a new 30" water transmission main. From 7 AM to 5 PM
- Ashton Rd from Mcintosh Rd to Pinkney Ave
- Ashton Rd at Ruby Ln
The public is urged to use caution around any construction activity.
Lane Closure Information: From March 6, 2026 Through March 13, 2026
Lane closure/shift needed to perform 12" forcemain offset. From 12 AM to 12 AM
- Proctor Rd from Honore Ave to Cattlemen Rd
The public is urged to use caution around any construction activity.
Lane Closure Information: From March 9, 2026 Through March 20, 2026
Lane closure required for paver removal and replacement. From 12 AM to 12 AM
- Fruitville Rd at Sarasota Center Blvd
The public is urged to use caution around any construction activity.
Lane Closure Information: From Early 2022 through Early 2027
The Florida Department of Transportation (FDOT) District One is conducting a Design-Build project to widen River Road (SR 777) from north of US 41 to south of I-75. The project limits fall within Sarasota County. FDOT determined that widening SR 777 from two lanes to six lanes from north of US 41 to south of I-75 will meet travel demand and enhance safety along this section. The project length is approximately 5.06 miles.
In addition to building a new six-lane roadway, the contractor is constructing drainage and safety improvements, shared-use paths, wildlife crossings, signing and pavement markings, lighting, signalization, and Intelligent Transportation System (ITS) features with raised medians and intersection improvements.
Road embankment installation continues on the northbound roadway from Aucilla Drive to US 41. As embankment is completed, drainage installations, subgrade mixing, curb placement, and roadway grading will continue. Sod installation, signal, ITS, and lighting work are ongoing. Trucks will be crossing the road at various locations using intermittent flagging operations. Pothole maintenance will continue as necessary on all current travel ways through the project.
Drivers should exercise caution and be aware of construction vehicles entering and exiting the roadway throughout the duration of the construction. Variable message signs will be in place to alert drivers that work is underway.
Anticipated completion for this project is Early 2027.
Road & Lane Closure Information: From Early 2025 through Early 2029
he Florida Department of Transportation (FDOT), along with Sarasota County, has identified the need to make improvements to the I-75 / Fruitville Road (SR 780) interchange to improve highway operations, safety, and regional mobility.
The interchange improvements include the design of a Diverging Diamond Interchange (DDI), which will significantly reduce delay on Fruitville Road, and reduce the number of conflict points to improve overall safety for all users. The DDI also offers the ability to accommodate future traffic volume growth. This project has been advanced as a part the Moving Florida Forward Infrastructure Initiative.
Improvements include:
- Reconstruct interchange from the existing partial cloverleaf design to a diverging diamond interchange (DDI)
- Widen about 2 miles of I-75, from Palmer Boulevard to north of Fruitville Road, to a six-lane highway with three through lanes per direction
- Reconstruct I-75 bridges over Fruitville Road
- Reconstruct I-75 southbound bridge, and widen I-75 northbound bridge, over Palmer Boulevard
- Widen I-75 bridges over Main A Canal
- Install emergency stopping sites on off-ramps
- Widen Fruitville Road from Honore Avenue to east of Coburn Road
- Install 7-foot buffered bike lanes and 6-foot sidewalks on Fruitville Road
- Replace traffic signals on Fruitville Road at Paramount Drive, Cattlemen Road, and Lakewood Ranch Boulevard
- Install new lighting on Fruitville Road
- Construct noise wall on I-75 northbound from Bee Ridge Road on-ramp to just north of Main A Canal
- Relocate tower
Drivers should exercise caution and be aware of construction vehicles entering and exiting the roadway throughout the duration of the construction. Variable message signs will be in place to alert drivers that work is underway.
Anticipated completion for this project is Early 2029.
Project Website
