What will
happen? |
When? |
Close Data Collection
In October 2009, the Cooperative Technical
Partners (CTP) received LiDAR product from the State of Florida; CTP completes
Quality
Assurance by August 2011*;
CTP conducts public meetings,
SWFWMD collects comments from GIS map products
(Floodplain Map Viewer) September 2011*
SWFWMD Floodplain Map Viewer at
www.watermatters.org
|
Spring 2012* |
Preliminary D-FIRM
SWFWMD provides a
contractor with all data collected.
Contractor produces a Preliminary D-FIRM. CTP
staff from all
jurisdictions finds product reasonable for
public review.
|
Summer 2012* |
90 Day Appeal and
Protest
CTP staff
presents Preliminary D-FIRM to local
officials to
approve and schedule a coordinated
jurisdictional 90 Day
Appeal and Protest Period. Individual
notifications occur,
public meetings and assistance to comment
(Protest) and/or
Appeal (scientific dispute).
The Preliminary D-FIRM product will be
made available online (website to be
determined).
|
Fall 2012* |
FEMA and
Local Adoptions
Any
Appeals and/or Protests received are
investigated for
validity by FEMA to change the
Preliminary D-FIRM. FEMA
approves a Final Digital Flood Insurance
Rate Map and
accompanying Flood Insurance Study. Upon
adoption all
federal, state and local regulations are
applicable.
|
Spring 2013* |