Link to ScGov.Net Sarasota County Government Online                                                         Perform Search
Call Center 
941-861-5000                            

County A-Z                        
Calendar of Events          
Meetings and Agendas    
Careers                            
Waterways Program
Environmental Home
Water Home
Waterways Program Home
Sediment Abatement Studies
Waterways Program Documents
Waterways Program Process
Waterways Program Finance
Waterways Program Permitting Private Projects
Waterways Program FAQs
 
Sarasota County Links
       Access Sarasota TV Live
       All Hazards Preparation
       GIS Mapping
       Parks and Recreation
       SCAT Bus System
 

 

Sarasota County Watersheds
South Creek Bayou #1

  South Creek Bayou #1 map

Milestone

Date

67 percent of first petition delivered to county

Unknown

Feasibility report finalized

Jan.27, 2005

Neighborhood meeting (design and cost estimate)

Feb. 16, 2005

67 percent  of second petition delivered to county

March 1, 2005

County Commission Hearing

Nov. 9, 2005

Application to FDEP

Aug. 8, 2006

FDEP approval

Jan. 5, 2007

Project advertised

Oct. 31, 2009

Bid Opening

Dec. 12, 2009

Commissioners approve construction contract

 

Construction begins

 

Project Complete

 

Project Update – October 2009

The South Creek Waterways Maintenance Project had to be re-advertised because only one dredge contractor bid on the project and then withdrew from the project one week before the contract was to go to the county commission for consideration. The contractor’s decision was based on difficulties they were having in locating a site for dewatering the dredged sediment prior to hauling it to the landfill. 

A county crew obtained water depth data in March of 2009. The data was collected within the proposed project area as well as in existing mooring areas (outside of the project area).

The project is intended to provide a channel that varies in width between 15 and 30 feet, with a depth of five feet at mean low water. Any additional dredging is the responsibility of the property owners and must be properly permitted. Property owners are encouraged to begin the permitting process at this time, March 2009, to ensure that the permits are issued prior to the county project completion so that the county's dredge contractor can be utilized by property owners for their dredging. The project will be required to be completed and verified prior to the contractor doing any additional private dredging.

The South Creek Bayou 1 project has been bundled with two other dredging projects. Should the county receive an acceptable bid, the South Creek Bayou 1 project will be either the second or third project dredged. By bundling the project with others, it is anticipated that a cost savings will be realized through a reduced mobilization/demobilization cost.

Link to ScGov.Net

Sarasota County, Florida  |  941-861-5000  |  Jobs   |   Media   |   Privacy Policy   |   Webmaster   |   Employee