Link to ScGov.Net Sarasota County Government Online                                                         Perform Search
Call Center 
941-861-5000                            

County A-Z                        
Calendar of Events          
Meetings and Agendas    
Careers                            
Waterways Program
Environmental Home
Water Home
Waterways Program Home
Sediment Abatement Studies
Waterways Program Documents
Waterways Program Process
Waterways Program Finance
Waterways Program Permitting Private Projects
Waterways Program FAQs
 
Sarasota County Links
       Access Sarasota TV Live
       All Hazards Preparation
       GIS Mapping
       Parks and Recreation
       SCAT Bus System
 

 

Sarasota County Waterways Program
Pirate's Pass

  Pirates Pass map

Milestone

Date

67 percent of first petition delivered to county

June 14, 2005

Feasibility report finalized

January 2007

Neighborhood meeting (design and cost estimate)

March 28, 2007

67 percent of second petition delivered to county

 

County Commission Hearing

 

Application to FDEP

 

FDEP approval

 

Project advertised

 

Bid Opening

 

Commissioners approve construction contract

 

Construction begins

 

Project Complete

 

Project Update – October 2009 
At a March 28, 2007, neighborhood meeting, county staff and project consultants (PBS&J) presented
the feasibility report, project design and cost estimates to the property owners.   

Following that meeting, a Project Unit Approval Petition was mailed to the 12 property owners. In order for the project to proceed, 67 percent of the benefiting property owners must sign, notarize and return the petition to the county.

The number of required petitions is eight. To date, no petitions have been received.
 