Link to ScGov.Net Sarasota County Government Online                                                         Perform Search
Call Center 
941-861-5000                            

County A-Z                        
Calendar of Events          
Meetings and Agendas    
Careers                            
Waterways Program
Environmental Home
Water Home
Waterways Program Home
Sediment Abatement Studies
Waterways Program Documents
Waterways Program Process
Waterways Program Finance
Waterways Program Permitting Private Projects
Waterways Program FAQs
 
Sarasota County Links
       Access Sarasota TV Live
       All Hazards Preparation
       GIS Mapping
       Parks and Recreation
       SCAT Bus System
 

 

Sarasota County Watersheds
Phillippi Creek - Tuttle to Hyde Park

  Phillippi Creek - Tuttle to Hyde Park map

Milestone

Date

67 percent of first petition delivered to county

Dec. 2, 2003

Feasibility report finalized

June 2008

Neighborhood meeting (design and cost estimate)

March 11, 2009

80 percent of second petition delivered to county

 

County Commission Hearing

 

Application to FDEP

 

FDEP approval

 

Project advertised

 

Bid Opening

 

Commissioners approve construction contract

 

Construction begins

 

Project Complete

 

Project Update – October 2009

The feasibility study has been completed and received by county staff. 

A neighborhood meeting was held on March 11, 2009 from 6 - 8 p.m. at the South Gate Community Center. County staff and the project engineer hosted the meeting and presented the feasibility study, the proposed dredge channel and the cost estimate.

On April 24, 2009, staff mailed the Project Unit Approval Petition to the 134 project properties via certified mail. Property owners who support the project need to sign, notarize the petition and submit it to: Paul Semenec, Capital Management Services, 1001 Sarasota Center Blvd., Sarasota, FL 34240. Property owners who do not support the project can simply disregard the petition. No action is needed on their part.

The project will be on hold until the required number of petitions (107, which is 80 percent of the 134 properties) is received. To date, staff has received one petition in support of this project.

 