Link to ScGov.Net Sarasota County Government Online                                                         Perform Search
Call Center 
941-861-5000                            

County A-Z                        
Calendar of Events          
Meetings and Agendas    
Careers                            
Waterways Program
Environmental Home
Water Home
Waterways Program Home
Sediment Abatement Studies
Waterways Program Documents
Waterways Program Process
Waterways Program Finance
Waterways Program Permitting Private Projects
Waterways Program FAQs
 
Sarasota County Links
       Access Sarasota TV Live
       All Hazards Preparation
       GIS Mapping
       Parks and Recreation
       SCAT Bus System
 

 

Sarasota County Watersheds
Phillippi Cove

  Phillippi Cove map

Milestone

Date

67 percent of first petition delivered to  county

July 22, 2003

Feasibility report finalized

December 2004

Neighborhood meeting (design and cost estimate)

May 26, 2005

Project Unit Approval Petition mailed by county

Unknown

67 percent of PUAP delivered to county

June 27, 2005

County Commission Hearing

Oct.11, 2005

Application to FDEP

May 26, 2006

FDEP approval

Nov. 20, 2006

Bid documents to Procurement office

Unknown

Project advertised

July 31, 2007

Bid Opening

Nov. 16, 2007 (second opening)

Commissioners approve construction contract

April 8, 2008

Construction begins

May 16, 2008

Project Complete

September 2008

Project Update – October 2009

In April 2008, the Sarasota County Commission approved the maintenance dredge construction contract with Energy Resources, Inc., from Chesterfield, Missouri. Construction began in June 2008 and was completed within two weeks. Disposal of the dredged sediment at the Sarasota county landfill and restoration of the dewatering site was completed in August 2008.

At a Dec. 9, 2008, public hearing, the county commission approved Ordinance 2008-123, which updated the legal sketch and description of the project unit, revised the definition of project unit and introduced a definition for funding district. The commission also approved a resolution declaring a notice of intent for the levy, collection and enforcement of non-ad valorem assessments to pay for the maintenance dredge project. In addition, following the public hearing, the commission approved agreements with the Sarasota County Property Appraiser and Tax Collector for the respective levy and collection of the non-ad valorem assessments.

At a June 10, 2009 public hearing, staff presented the county commission with the initial rate resolution and estimated assessment amounts. The commission unanimously approved the resolution. The assessments were finalized during the September 2009 budget meetings and the first of ten annual assessments appeared on the November 2009 tax bill.

 