North Lake
Shore Drive map

|
Milestone |
Date |
|
67 percent of first petition delivered to
county |
May 13, 2003 |
|
Feasibility report finalized |
October 2004 |
|
Neighborhood meeting (design
and cost estimate) |
Oct. 23, 2004 |
|
Project Unit Approval Petition mailed by
county |
Unknown |
|
67 percent of PUAP delivered to
county |
Unknown |
|
County Commission Hearing |
April 13, 2005 |
|
Application to FDEP |
Feb. 6, 2006 |
|
FDEP approval |
Dec. 7, 2006 |
|
Bid documents to Procurement office |
Unknown |
|
Project advertised |
Oct. 12, 2007 |
|
Bid Opening |
Nov. 7, 2007 |
|
Commissioners approve construction contract |
|
|
Construction begins |
|
|
Project Complete |
|
North Lake Shore Project Update –
October 2009
As of December 2008 this project has been
cancelled.
|