Link to ScGov.Net Sarasota County Government Online                                                         Perform Search
Call Center 
941-861-5000                            

County A-Z                        
Calendar of Events          
Meetings and Agendas    
Careers                            
Waterways Program
Environmental Home
Water Home
Waterways Program Home
Sediment Abatement Studies
Waterways Program Documents
Waterways Program Process
Waterways Program Finance
Waterways Program Permitting Private Projects
Waterways Program FAQs
 
Sarasota County Links
       Access Sarasota TV Live
       All Hazards Preparation
       GIS Mapping
       Parks and Recreation
       SCAT Bus System
 

 

Sarasota County Watersheds
Matheny Creek

  Matheny Creek map

Milestone

Date

67 percent of first petition delivered to county

May 13, 2003

Feasibility report finalized

January 2004

Neighborhood meeting (design and cost estimate)

March 23, 2004

Project Unit Approval Petition mailed by county

Unknown

67 percent of PUAP delivered to county

Unknown

County Commission Hearing

Oct. 27, 2004

Application to FDEP

Oct. 12, 2005

FDEP approval

Sept. 12, 2006

Bid documents to Procurement office

Unknown

Project advertised

Jan. 8, 2007

Bid Opening

Feb. 7, 2007

Commissioners approve construction contract

April 10, 2007

Construction begins

July 5, 2007

Project Complete

March 2008

Matheny Creek Project Update – October 2009

In April 2007, the Sarasota County Commission approved the maintenance dredge construction contract with Marine Contracting Group, Inc., from Punta Gorda, Florida. Construction began in July 2007 and was completed in November 2007. Remediation (additional dredging) was completed in February 2008 to address several owners concerns. 

On Dec. 16, 2008, staff received authorization from the Sarasota County Commission to advertise a public hearing regarding an Initial Rate Resolution to establish the assessment methodology for the levy of non-ad valorem property assessments to fund the completed maintenance dredge project. The Jan. 13, 2009, public hearing was continued by the commissioners three times to allow staff to discuss project issues and remediation of those issues with property owners.

At a May 27, 2009 public hearing, staff presented the commission with the initial rate resolution and estimated assessment amounts. The commission unanimously approved the resolution. The assessments were finalized during the September 2009 budget meetings and the first of ten annual assessments appeared on the November 2009 tax bill.

 