Forked Creek Dale Lakes map

|
Milestone |
Date |
|
67 percent of first petition delivered to
county |
Sept. 30, 2005
|
|
Feasibility report finalized |
July 2007 |
|
Neighborhood meeting (design
and cost estimate) |
June 12, 2008 |
|
67 percent of second petition delivered to
county |
|
|
County Commission Hearing |
|
|
Application to FDEP |
|
|
FDEP approval |
|
|
Project advertised |
|
|
Bid Opening |
|
|
Commissioners approve construction contract |
|
|
Construction begins |
|
|
Project Complete |
|
Project Update –
October 2009
The
feasibility report was completed in May 2008. The report
includes the feasibility report for the Forked Creek North
Branch project since the Dale Lakes project area is upstream of
the North Branch project area. The Dale Lakes project will not
connect to navigable water unless the North Branch project is
completed.
At a June
12, 2008, neighborhood meeting, county staff and the project
consultant (DMK Associates) discussed the project with property
owners.
In August
2008, county staff determined that the boat lots associated with
the Blue Dolphin Estates subdivision cannot be legally accessed.
Therefore, those properties have been dropped from the project
unit.
In early September 2008, a Project Unit Approval Petition
was sent by certified mail to the 60 benefiting property owners.
In order for the project to proceed, 67 percent of those
property owners must sign, notarize and return the petition to
the county. The required number of petitions is 40. To date 14
completed
petitions have been received. |