Baywood Canal
map

|
Milestone |
Date |
|
67 percent of first petition delivered to
county |
May 2, 2003 |
|
Feasibility report finalized |
Feb. 2004 |
|
Neighborhood meeting (design
and cost estimate) |
April 28, 2004 |
|
Project Unit Approval Petition mailed by
county |
Unknown |
|
67 percent of PUAP delivered to county |
June 4, 2004 |
|
County Commission Hearing |
Dec. 8, 2004 |
|
Application to FDEP |
Dec. 28, 2005 |
|
FDEP approval |
Nov. 29, 2006 |
|
Bid documents to Procurement office |
Jan. 2009 |
|
Project advertised |
Oct. 31, 2009 |
|
Bid Opening |
Dec 12, 2009 |
|
Commissioners approve construction contract |
|
|
Construction begins |
|
|
Project Complete |
|
Project Update –
October 2009
Based on a
request from property owners, county staff requested a change to the project
authorization issued by the Florida Department of Environmental Protection (FDEP).
The authorization was amended in June 2007 to include additional dredging at the
end of the northern-most canal, adjacent to Schooner Bay.
The
Schooner Bay Association plans to remove the finger piers extending from the
bulkhead at the end of the canal prior to construction. This allows the dredge
footprint to extend another 17-feet northward towards the end of the canal.
When
county staff drafted the project contract documents in mid-2007, a temporary
dredge and construction easement was also drafted. The easement was approved by
the county attorney in January 2008. The Sarasota County Real Property office
initiated contact with the owner of submerged land at the mouth of the Baywood
canal in order to obtain an easement which would allow privately-owned sediment
to be removed.
In May
2008, the owner of the submerged land contacted the county requesting revisions
to the easement language. Following review of the request by the county
attorney’s office, FDEP was contacted to verify that the state does not claim
ownership of the submerged land at the mouth of the Baywood canal.
A response
from FDEP has been received and a meeting was scheduled with additional county
staff to discuss the project. Based on the information received from FDEP,
Sarasota County Survey/Mapping staff was able to accurately depict the
privately-owned submerged land and verify that an easement is needed. The
Sarasota County Real Property office received executed easement documents from
the owner of the submerged land in July 2008, and the paperwork is currently
being reviewed by the county attorney.
The construction plans and contract documents for the Baywood
Canal project have been finalized. Advertisement (to solicit
bids from dredge contractors) of the construction project was
originally scheduled for Jan. 16, 2009. Due to unforeseen
issues, the advertisement of the project was postponed for up to
30 days. On Feb. 2, 2009, staff was directed to proceed with
project advertisement. The project was advertised on Feb. 6,
2009, and submitted bids were opened on April 15, 2009. In June
2009, staff determined that the project was to be re-advertised
with a requirement for hydraulic dredging. The project was
re-advertised. Submitted bids were opened on July 29, 2009.
Staff has determined that neither of the two companies
submitting a bid met the minimum qualifications required for the
project.
The Baywood Canal project has been bundled with two other
dredging projects. Should an acceptable bid be received, the
Baywood Canal project will be the first of the three projects to
be dredged. By bundling the project with others, it is
anticipated that a cost savings will be realized through a
reduced mobilization/demobilization cost. Once
a dredge contractor has been selected, a neighborhood meeting
will be scheduled to allow staff to review the project with
property owners and answer questions. County regulatory staff
will also be present to discuss additional private dredging
outside of the county project area. |