Nokomis Water Line Project
| Nokomis Water Lines in
Areas 3A, 3B, 3C East, 3C West and 3D are
Ready for Hookup |
- Central drinking water is
now ready in the areas identified above. A safe, reliable water supply is available.
These residents will no longer
have to worry about salt-water intrusion, droughts or
mineral deposits in laundry and hot water tanks.
- It was a two year project,
scheduled from June 2007 until
June 2009. The project was complete in January 2009, six
months ahead of schedule.
- Assessment dollar amounts will not
exactly be known until the completion of construction.
- Call 941-861-0569 for hookup
information.
Construction is now beginning in the Northeast section (see
map below)
- Construction is expected to
be complete in January, 2010.
- The final costs of
construction will not be known until the project is
complete, but a portion of the assessment cost will be
funded from the county's penny surtax (1-cent sales tax).
- The contractor, Stately
Contractors, Inc. is working in the Northeast Nokomis area.
As work comes closer to your house, a green door hanger and
a flag will be distributed. Please read the information.
- Property owners, via the
door hanger, will be asked to place the flag in the yard
near the edge of the road to indicate where they would like
the water meter. If no flag is placed in the yard,
experienced crews will select the most logical location.
- During construction,
temporary occasional driveway and lane closures will be
necessary. Flagmen will be present to direct traffic when
necessary.
- Work will not be done on
your private property, but in the adjacent county right of
way or easements near the road.
Click on an area to open a .pdf
version of the map in a new window.
 |
|
|
|
|
|
|