Project Name |
|
Status Indicator |
|
Central Wastewater Collection System (design) |
|
Begin preparation for Call for Professional Services in
Aug. 2009. |
|
Water Service Program to Support the Wastewater Ext.
Phase I |
|
Begin preparation for Call for Professional Services in
Aug. 2009. |
|
Transit Stop Improvements |
|
90% plans received. 100% plans by 6/25/09. |
|
Phillippi Creek STW Quality |
|
Call for design engineering services to be issued in
June 2009. Grant coordination has delayed advertisement.
|
|
Dona Bay Hydrology management. |
|
Design under way (KHA) with scheduled completion in Aug.
2010. |
|
Alligator Creek STW Quality |
|
Professional services contract (Watermark Engineering)
not authorized at May 26, 2009, BCC meeting. Reviewing
PSRC process. Expect additional action at June 10, 2009
BCC meeting. |
|
Red Bug Slough Restoration |
|
Design underway (PBS&J) with scheduled completion in
April 2010. |
|
Sediment Abatement and stabilization |
|
Professional services contract negotiations under way
(Progressive Water Services) for both Lemon Bay and
Roberts Bay. Scheduling for BCC approval in July 2009.
|
|
Selby Library Remodel, Phase 1 & 2 |
|
Purchase Order issued to Totems for $146,295. Design
completion anticipated in Sept. 2009. |
|
Urfer Family Park (a.k.a. Honore Trail Park) |
|
Phase 2 (CB Wilson House) construction contract awarded
on 05/26/09. Construction expected to be complete in
June 2010. |
|
Library Technology Surtax III |
|
Contract for AMH systems has been reviewed by
Procurement and sent back to the vendor for comments.
The RFP Review Team will be meeting shortly to discuss
changes with the vendor before sending the contract on
to Legal for first review. The Project Manager for the
AMH portion is Darlene Frazee. |
|
Elsie Quirk Remodel |
|
Expected to advertise July 2009. |
|
North Port Health & Family Ser |
|
Work assignment issued to CPH for $109,500. Expected to
advertise in Aug. 2009. |
|
New Englewood Facility Design |
|
Call for Professional Services advertised May 27, 2009.
Proposals received June 23, 2009. PSRC to be scheduled.
|
|
History Museum/BCC Challenge G |
|
Begin negotiating scope and fee with Greg Hall
Architects in July 2009. |
|
Spoil Island Restoration |
|
May 13, 2009 BCC direction to delay new project starts
and reallocate $600,000 ESP dollars to other projects.
$500,000 remaining to fund construction of Palmer Point
Restoration expected to bid in Fall 2009. Other projects
on-hold. |
|
New Siesta Beach Site (Wood) |
|
Closed on property purchase. No additional ESP work
required. Funds to be reallocated to other Parks Surtax
projects. Project complete. |
|
Street Tree - Tree Canopy Program |
|
Various checkbook projects completed w/ongoing
establishment periods (Oxford Drive, Palm Terrace and
Oak Terrace), under construction (East Venice,
Arterials-Re/Afforestation and Kensington Park), and in
design (Fruitville East, Jacaranda roundabout, N
Cattlemen, Fruitville-Cob-Deb, Honore, Gold Ave., Gulf
Gate, Beneva, Old Miakka and Honore 5). Design and
construction authorizations continue through existing
continuing services contracts and annual agreements. |
|
Fruitville Road Coburn Sarasota Center |
|
Phase 1 from Debrecen to east of Tatum bid opening
5/27/09, and construction award is scheduled for July.
Phase 2 is scheduled to be advertised the week of
6/22/09. |
|
Honore Bee Ridge to Fruitville |
|
The contract for preliminary design was awarded May
27th. 60 days duration for this contract. |
|
Blackburn Point Park Addition |
|
Design under way (KHA) with scheduled completion in Dec.
2009. |
|
Sidewalks Bee Ridge/Wilkinson |
|
Sidewalk on the north side of Wilkinson being worked on.
Construction is 85% complete. Contract end date Sept.
13, 2009. |
|
Sidewalks Gulf Gate |
|
Construction contract was awarded June 9, 2009.
Construction will start on Ashton Road on 6/22/09.
Substantial completion by 12/16/09. |
|
Sidewalks North Sarasota |
|
Final sketches have been completed, and ROW acquisition
currently in progress. SWFWMD permit has been approved.
Staking and reappraisal start next month. To be
advertised in Nov.0209 |
|
Sidewalks PCSSRP Area D |
|
Sidewalk construction started 4/27/09. Sidewalk on the
south side of Webber Street being worked on, from
Tanglewood going east. Construction ends April 2010.
|
|
Turtle Beach Renovations |
|
Call needed for design services. Anticipated to go to
Procurement in July 2009. |
|
Baywalk at Ken Thompson Park |
|
Design and construction to be bundled in Coastal
Facilities unit price contract. Bids under review.
Scheduling contract authorizations at July 7, 2009 BCC
meeting. |
|
Blind Pass Beach Restrooms |
|
Specific Authorization to CPH for $207,250 approved on
11/18/08. Design completion anticipated in Dec. 2009.
|
|
Fruitville Park Athletic Field |
|
Work assignment issued to Totems for $96,914. Design
completion expected in July 2009. |
|
Manasota Beach Restrooms |
|
BCC approval of Totems contract in the amount of
$258,800 for design, permitting and construction
administration on 3/17/09. Design completion anticipated
Dec. 2009. |
|
South Lido Beach Restrooms |
|
Work assignment issued to Totems for $99,707. Design
completion expected in July 2009. Construction to begin
in April 2011 when funding is expected to be available.
|
|
S. Lido Trails |
|
Design and construction to be bundled in Coastal
Facilities unit price contract. Bids under review.
Scheduling contract authorizations at July 7, 2009 BCC
meeting. |
|
North Jetty Beach Park restrooms/concession |
|
BCC approval of CPH contract in the amount of $214,643
for design, permitting and construction administration.
Public meeting held on June 3, 2009. Construction to
begin in April 2011 when funding is expected to be
available. |
|
Caspersen Beach Restrooms |
|
BCC approval of Totems contract in the amount of
$277,595 for design, permitting and construction
administration on 3/17/09. Design completion anticipated
in Dec. 2009. |
|
Nokomis Beach Improvements |
|
Work assignment issued to Greg Hall Architects for
$52,015. Design completion anticipated for Oct 2009.
|
|
Playground additions and improvements |
|
Projects complete. |
|
Red Bug Slough Preserve |
|
Negotiating work assignment (KHA) for authorization.
Anticipate design start July 2009. |
|
Sleeping Turtles Preserve (Ligon) |
|
Issued work assignment to King Engineering for 94,141.
Design completion anticipated for July 2009.
|
|
Beach Access Improvements / Shoreline Access Phase I |
|
Design for Beach Access 12 underway (ECE) with scheduled
completion in Dec. 2009 . Construction on BA #3
completed in April 2009. Wharf/Vamo Road conceptual
design underway (Wilson Miller) to be completed in Aug.
2009. |
|
Benderson Park |
|
County to meet with developer to determine who takes
lead in design. If County, then Call for Professional
Services will be needed. |
|
Boardwalk Replacements - Alligator Creek (design,
construction |
|
Design and construction to be bundled in Coastal
Facilities unit price contract. Bids under review.
Scheduling contract authorizations at July 7, 2009 BCC
meeting. |
|
Boardwalk Replacements - Chauncey (construction) |
|
In-house design under way. Construction via Coastal
Facilities unit price contract. Bids under review.
Scheduling contract authorizations at July 7, 2009 BCC
meeting. |
|
Siesta Beach Improvements (design) |
|
Concept plan approved by BCC on May 12, 2009. Begin
preparation of Call for Professional Services for design
in June 2009. Advertise Call in July 2009. |
|
Boardwalk Replacements - Lemon Bay (design, construction
) |
|
Design and construction to be bundled in Coastal
Facilities unit price contract. Bids under review.
Scheduling contract authorizations at July 7, 2009 BCC
meeting. |
|
Boardwalk Replacements - Brohard (construction) |
|
In-house design under way. Construction via Coastal
Facilities unit price contract. Bids under review.
Scheduling contract authorizations at July 7, 2009 BCC
meeting. |
|
Boardwalk Replacements - Caspersen Beach (design,
construction ) |
|
Design and permitting under way (CTC). Construction via
Coastal Facilities unit price contract. Bids under
review. Scheduling contract authorizations at July 7,
2009 BCC meeting. |
|
Ben Franklin Drive Trail |
|
Design under way (PBS&J) with scheduled completion in
Nov. 2009. |
|
Road Resurfacing- Surtax 3 |
|
Punch list items being worked on for the Lockwood Ridge
and around Area A resurfacing contracts. Additional
streets being reviewed to be added to the Beneva Road
resurfacing contract. |
|
Bridge R&R- Surtax 3 |
|
See below |
|
Blackburn Point Bridge |
|
Repair work has been complete. Bridge was opened to
vehicular traffic on 6/18/09 |
|
Central Ave and Myrtle St. bridges |
|
30% plan comments complete, 90% plans by Aug. 2009
|
|
Lockwood Ridge Bridge |
|
30% plan comments complete, 75% plans by July 2009
|
|
Raymond Road Bridge |
|
75% plans received. |
|
Honore (Pinebrook) |
|
JPA being worked on with FDOT. Money transfer to FDOT by
Oct. 2009 |