Project Name |
|
Status Indicator |
|
Library Technology Surtax III |
|
Contract for AMH systems is anticipated to be approved
by the BCC in October. The Project Manager for the AMH
portion is Darlene Frazee. |
|
Phillippi Creek STW Quality |
|
Call for design engineering services to be issued in Nov
2009. FDEP Grant executed by BOCC on Sept. 8, 2009.
|
|
Dona Bay Hydrology Mgmt. |
|
Design under way (KHA) with scheduled completion in Aug.
2010. |
|
Alligator Creek STW Quality |
|
Design under way (Watermark) with scheduled completion
in March 2010. |
|
Red Bug Slough Restoration |
|
Design underway (PBS&J) with scheduled completion in
April 2010. |
|
Sediment Abatement and Stabilization |
|
Design for both Roberts and Lemon Bay under way
(Progressive Water) with scheduled completion in July
2010. |
|
Spoil Island Restoration |
|
$1.1MM surtax dollars retained in program for FY-10
budget. Palmer Point Restoration construction expected
to bid in Fall 2009. |
|
New Siesta Beach Site (Wood) |
|
Closed on property purchase. No additional ESP work
required. Funds to be reallocated to other Parks Surtax
projects. ESP element of project complete. |
|
Street Tree - Tree Canopy Program |
|
Various checkbook projects completed w/ongoing
establishment periods (Oxford Drive, Palm Terrace, Oak
Terrace, Kensington Park), under construction (East
Venice), and in design (Fruitville East, Jacaranda
roundabout, N. Cattlemen, Fruitville-Cob-Deb, Honore,
Gulf Gate, Beneva, Old Miakka and Honore 5). Design and
construction authorizations continue through existing
continuing services contracts and annual agreements. |
|
Blackburn Point Park Addition |
|
Design under way (KHA) with scheduled completion in Dec.
2009. |
|
Baywalk at Ken Thompson Park |
|
Partial construction underway with Ram Marine. Unit
Price Contract Work assignment to be issued in Nov. 2009
for remaining design and construction. Construction
scheduled to be complete in March 2010. |
|
S. Lido Trails |
|
Unit Price Contract Work assignment to be issued in Nov.
2009 for design and construction. Construction to be
complete in May 2010. |
|
Beach Access Improvements / Shoreline Access Phase I |
|
Design for Beach Access 12 underway (ECE) with scheduled
completion in Dec. 2009 . Wharf/Vamo Rd conceptual
design completed (Wilson Miller). Final design underway
(WilsonMiller) with expected completion in December
2009. Beach Access 12 to be discussed at 11/5/09 SKA
meeting. |
|
Boardwalk Replacements - Alligator Creek (design,constr) |
|
Unit Price Contract Work assignment to be issued in Dec
2009 for design and construction. Construction scheduled
to be complete in April 2010. |
|
Boardwalk Replacements - Chauncey (const.) |
|
Permitting underway with PBS&J. Construction via Coastal
Facilities unit price contract. Construction scheduled
to be complete in Dec. 2009. |
|
Boardwalk Replacements - Lemon Bay (design,
construction) |
|
Unit Price Contract Work assignment to be issued in Dec.
2009 for design and construction. Construction scheduled
to be complete in July 2010. |
|
Boardwalk Replacements - Brohard (construction) |
|
Permitting underway with PBS&J. Construction via Coastal
Facilities unit price contract. Construction scheduled
to be complete in Dec. 2009. |
|
Boardwalk Replacements - Caspersen Beach (design,
construction) |
|
Design and permitting under way (CTC). Construction via
Coastal Facilities unit price contract. Construction
scheduled to be complete in March 2011. |
|
Ben Franklin Drive Trail |
|
Design under way (PBS&J) with scheduled completion in
November 2009. Currently permitting with city of
Sarasota. Construction to be completed through unit
price contracts (Derr and Coastal Construction),
Construction scheduled to be complete in April 2011. |
|
Selby Library Remodel, Phase 1 & 2 |
|
Purchase Order issued to Totems for $146,295. Design
completion anticipated in Dec. 2009. |
|
Urfer Family Park (f.k.a. Honore Trail Park) |
|
Phase 2 (CB Wilson House) construction contract awarded
on 05/26/09. Construction expected to be complete in
June 2010. Dedication scheduled for Nov. 14, 2009.
|
|
Elsie Quirk Remodel |
|
Advertise Aug. 15, 2009. Bids opened Sept. 30, 2009.
Scheduled for BCC award Nov 17, 2009. |
|
North Port Health and Family Servicesr |
|
Advertise Aug. 15, 2009. Bids opened Sept 16, 2009. BCC
award scheduled for Nov. 18,2009. |
|
New Englewood Facility Design |
|
PSRC held on July 27, 2009. Fleishman-Garcia was the
selected firm. Design contract award scheduled for
10/2709. |
|
History Museum/BCC Challenge G |
|
Determining scope needs. Negotiating with Totems for
preliminary study. |
|
Turtle Beach Renovations |
|
Call needed for design services. Anticipate advertising
in late Nov. 2009. |
|
Blind Pass Beach Restrooms |
|
Specific Authorization to CPH for $207,250 approved on
11/18/08. Design completion anticipated in Dec. 2009.
|
|
Fruitville Park Athletic Field |
|
Bids opened Sept. 30, 2009. Anticpate BCC award in Nov.
17, 2009. |
|
Manasota Beach Restrooms |
|
BCC approval of Totems contract in the amount of
$258,800 for design, permitting and construction
administration on 3/17/09. Design completion anticipated
Dec. 2009. |
|
South Lido Beach Restrooms |
|
Work assignment issued to Totems for $99,707. Design
completion expected in March 2010. Construction to begin
in April 2011 when funding is expected to be available.
|
|
North Jetty Bch Park RR/concession |
|
BCC approval of CPH contract in the amount of $214,643
for design, permitting and construction administration.
Construction to begin in April 2011 when funding is
expected to be available. |
|
Caspersen Beach Restrooms |
|
BCC approval of Totems contract in the amount of
$277,595 for design, permitting and construction
administration on 3/17/09. Design completion anticipated
in Dec. 2009. |
|
Nokomis Beach Improvements |
|
Work assignment issued to Greg Hall Architects for
$52,015. Bid opening scheduled for Nov. 18, 2009.
|
|
Playground additions and improvements |
|
Projects complete. |
|
Red Bug Slough Preserve |
|
Negotiating work assignment with Kimley-Horn. Anticipate
design start in Nov. 2009. |
|
Sleeping Turtles Preserve (Ligon) |
|
Issued work assignment to King Engineering for 94,141.
Anticipate design completion in Nov. 2009. |
|
Benderson Park |
|
Developer to complete concept plan. Concept plan
anticipated to be brought before the BCC in Dec 2009.
Call for Professional Services anticipated to be
advertised in Feb. 2010. |
|
Siesta Beach Improvements (design) |
|
Two-phase PSRC design selection process. first PSRC
(short-list top three) was on 9/14. The second PSRC
(oral presentations from top three) on hold due to
protest. Protest denied at 10/ 28 BCC. second PSRC
scheduled for Nov. 4. |
|
Central Wastewater Collection System (design) |
|
Anticipate advertising Call for Professional Services in
Nov. 09. |
|
Water Service Program to Support the Wastewater Ext.
Phase I |
|
Anticipate advertising Call for Professional Services in
Nov. 09. |
|
Transit Stop Improvements |
|
100% plans received. Using Unit Price contract,
construction starts early Nov. 09. Two additional design
work assignments for PBS&J and HDR currently being
processed. |
|
Fruitville Road Coburn Sarasota Center |
|
Construction contract for phase 1 from Debrecen to east
of Tatum was awarded on July 21; phase 1 construction
duration is 8 months. Phase 2 construction from East of
Tatum to Coburn Road was awarded on Sept. 8. |
|
Honore Bee Ridge to Fruitville |
|
The contract for final design and construction was
awarded on 7/21/09. The bridge construction is scheduled
to start the week of Nov. 2. Substantial completion by
Feb. 2011. |
|
Sidewalks Bee Ridge/Wilkinson |
|
Final completion certification in progress. |
|
Sidewalks Gulf Gate |
|
Construction contract was awarded June 9, 2009.
Construction is underway, Substantial completion by
12/16/09. |
|
Sidewalks North Sarasota |
|
SWFWMD permit has been approved. ROW acquisition
currently in progress. Necessity of Resolution to the
Board on 12/8/09. The project is scheduled to advertise
in Feb. 2010. |
|
Sidewalks PCSSRP Area D |
|
Sidewalk construction started 4/27/09. Construction ends
April 2010. |
|
Road Resurfacing- Surtax 3 |
|
All the resurfacing projects have been substantially
completed. Additional streets have been added to the
Beneva Road and Lockwood Ridge resurfacing contracts.
APAC is currently working on Lychee Road, the last
street on the added list. |
|
Bridge R&R- Surtax 3 |
|
See below |
|
Blackburn Point Bridge |
|
Repair work has been complete. Bridge was opened to
vehicular traffic on 6/18/09 |
|
Central Ave. and Myrtle St. Bridges |
|
100% plans received. Easements being acquired. Scheduled
to advertise in Nov. 09 |
|
Lockwood Ridge Bridge |
|
100% plans received. Advertised Oct. 21. Bid opening
scheduled for Nov. 25. |
|
Raymond Road Bridge |
|
100% plans received. Easements are being acquired.
Scheduled to advertise in Nov. 09 |
|
Honore (Pinebrook) |
|
LFA with FDOT was approved by the Board on Oct. 13,
2009. Funding is being transferred to FDOT.
|