|
Project Name |
Status Indicator |
|
Transit
Vehicle Purchase |
|
|
Sheriff's Modem Replacement |
Status
report of current systems (Sheriff and County) completed
and being reviewed for sustainability. The EOC will be
located at 1301 Cattlemen. Project on hold pending
County determination regarding main radio
infrastructure. |
|
Sheriff's Trunked radio |
Status
report of current systems (Sheriff and County) completed
and being reviewed for sustainability. The EOC will be
located at 1301 Cattlemen. Project on hold pending
County determination regarding main radio
infrastructure. |
|
Celery
Fields Economic Development |
|
|
Fairgrounds Economic Development |
|
|
Phillippi Creek STW Quality |
Design
under way (KHA) with scheduled completion in Jan 2012.
|
|
Dona
Bay Hydrology Mgmt. |
Design
under way (KHA) with scheduled completion in Jan 2012.
|
|
Alligator Creek STW Quality |
Construction underway. |
|
Red Bug
Slough Restoration |
Phase 1
design completed (PBS&J). Phase 2 with scheduled design
completion in Jan 2012. |
|
Sediment Abatement & stabilization |
Design
for both Roberts and Lemon Bay complete (Progressive
Water). Bid opened 8/24/11. |
|
Riverview Dr. Sediment - Baffle Boxes |
In
planning with Water Resources. |
|
Brother
Geneen Way Culvert |
County
funds to be used for construction in 2012. City of SRQ
managing complete project. |
|
Spoil
Island Restoration |
$710,000 surtax $ retained in program for FY-10 budget.
Palmer Point Restoration construction underway. |
|
Street
Tree - Tree Canopy Program |
Various
checkbook projects completed w/ongoing establishment
periods (Oxford Dr, Palm Terrace, Oak Terrace,
Kensington Park), and in design (Fruitville East,
Jacaranda roundabout, N Cattlemen, Fruitville-Cob-Deb,
Honore, Gulf Gate, Beneva, & Honore 5). Design and
construction authorizations continue through existing
continuing services contracts and annual agreements. |
|
Blackburn Point Park Addition |
Design
under way (KHA) with scheduled completion in Jan 2012.
Bid docs in preparation for March 2012 advertisement.
|
|
S. Lido
Trails |
Portion
of funds reallocated to other Surtax projects. Remaining
funds to be used for reconstruction of south structures
and north minor improvements. Permitting complete with
PBS&J. Construction underway. |
|
Beach
Access Improvements / Shoreline Access Phase I |
$300,000 reallocated to other Surtax projects. Design
for Beach Access 12 underway (ECE) complete. Phase 1,
Parking Lot Drainage Improvements under construction.
Phase 2, Maintenance Access with possible future
construction. County permitting in progress. |
|
Benderson Park |
Concept
plan approved by BCC on July 27, 2010. Benderson
Implementation Agreement approved 1/25/11. Preliminary
design BCC approved 10/25/11. |
|
Boardwalk Replacements - Alligator Creek (design,
construction) |
Construction complete. |
|
Siesta
Beach Improvements (design) |
Preliminary - 30% design underway (KHA) with scheduled
completion in Jan 2012. |
|
Boardwalk Replacements - Lemon Bay (design,
construction) |
Permitting complete. Construction underway. |
|
Boardwalk Replacements - Caspersen Beach (design,
construction) |
Construction complete. |
|
Ben
Franklin Drive Trail |
Design
complete (PBS&J). Partial construction may be completed
through unit price contracts or advertised bid. Reduced
scope of construction under evaluation due to partial
reallocation of Surtax III funds. |
|
Wharf
Road Dock & Fishing Pier |
Partial
Surtax project. Remaining funds through WCIND. Under
conceptual design with Parks & Rec. |
|
Transit
Maintenance Facility |
Construction of a new transit maintenance facility for
south Sarasota County transit service. |
|
Selby
Library Remodel, Phase 1 & 2 |
Purchase Order issued to Totems for $146,295. Contract
award to Dooley-Mack for $1,201,645 on 3/29/11. Project
complete. |
|
Urfer
Family Park |
Wilson
House complete. Design underway with PBS&J for
additional parking improvements. |
|
Gulf
Gate Library |
Harvard
Jolly is the selected design firm. Concept planning
contract to BCC in April 2011. Site selection occurred
9/14/11. Design contract award occurred 12/6/11.
Advertisement/solicitation for CM at Risk occurred
12/8/11. |
|
Library
Technology Surtax III |
Contract with Tech Logic approved by BCC
12/08/09. Contract Amendment 2 approved June 7, 2011.
Design of N. Port AMHS underway with BMK |
|
Elsie
Quirk Remodel |
Project
complete. |
|
Neighborhood Initiative Program |
Misc.
on-going project. |
|
North
Port Health & Family Services |
Project
complete. |
|
New
Englewood Facility Design |
Project
cancelled. |
|
History
Museum/BCC Challenge G |
Totems
conducting preliminary study. Anticipated to be complete
in late 2011. |
|
Nokomis
Neighborhood Improvements |
Design
for Nokomis Sidewalks project scheduled to start in Jan
2012. |
|
Turtle
Beach Renovations |
CPH the
selected firm. Due to Surtax III shortfall, Parks
re-evaluated and reduced design scope. Design contract
to CPH awarded on 3/15/11. PO not issued. Contract amend
reducing scope and fee scheduled for Jan 20121 BCC.
|
|
Blind
Pass Beach Restrooms |
Specific Authorization to CPH for $207,250 approved on
11/18/08. Design complete. Project shelved for future
construction. |
|
Fruitville Park Athletic Field |
Project
complete. |
|
Manasota Beach Restrooms |
Contract awarded to Magnum on 10/11/11. NTP issued
12/7/11. Project completion schedule for 9/1/12. |
|
South
Lido Beach Restrooms |
Work
assignment issued to Totems for $99,707. Design
complete. Spec Book process underway. Anticipate
advertising Jan 2012. |
|
North
Jetty Beach Park Restrooms/Concession |
BCC
approval of CPH contract in the amount of $214,643 for
design, permitting and construction administration.
Design complete. Spec Book process underway. Anticipate
advertising in Jan 2012. |
|
17th
St. Park Improvements |
No
project identified. |
|
Caspersen Beach Restrooms |
Construction contract awarded to Magnum for $1,433,930
on 3/29/11. Project completion scheduled for 2/15/12. |
|
Nokomis
Beach Improvements |
Project
complete. |
|
Red Bug
Slough Preserve |
Design
(KHA) complete. Construction contract to Coral Sands
with completion scheduled for 12/26/11. |
|
Sleeping Turtles Preserve (Ligon) |
Issued
work assignment to King Engineering for 94,141. Project
being shelved at owner's request. |
|
Bee
Ridge Park |
No
project identified. |
|
Tuscano
Park |
Real
Property investigating County ownership status and
access easements. Minor park improvements to be
completed by Feb 2012. Public meeting held on 8/9/11.
Design on minor improvements to be done in-house.
|
|
Lemon
Bay Playhouse |
No
activity. |
|
N.
County Sports Complex |
Project
funds moved to a higher priority Surtax project.
|
|
17th
Street BMX Renovation |
Minor
improvements by P&R to existing site underway.
|
|
Lime
Lake Neighborhood Park |
Project
complete. |
|
Snook
Haven Restroom |
Design
of sewer and water with Giffels-Webster underway.
|
|
Parks &
Recreation Natural Areas |
Additional funding for CIP 93027 Red Bug Slough Preserve
Restrooms. |
|
PCSSRP
Area N |
Phase 1
complete. Connection notices to go out cert. mail in Jan
2012. Phase 2 will advertise for construction bids in
Jan 2012.. |
|
Waterline Extension Area N |
Phase 1
complete. Connection notices to go out cert. mail in Jan
2012. Phase 2 will advertise for construction bids in
Jan 2012.. |
|
Central
Wastewater Collection System Extension |
Longer
range planning efforts will continue in the south county
area until such time as new TMDL Limits are established
by the EPA. |
|
Water
Service Program to Support the Wastewater Collection
System Extension |
Longer
range planning efforts will continue in the south county
area until such time as new TMDL Limits are established
by the EPA. |
|
Transit
Stop Improvements |
Batch
#6 is under design. |
|
Bee
Ridge Extension |
Design
underway. |
|
Traffic
Control Signal Prioritization |
Design
underway. |
|
Fruitville Road Coburn Sarasota Center |
Complete |
|
Honore
Bee Ridge to Fruitville |
Phase 3
construction underway. |
|
Sidewalks Gulf Gate |
Completed |
|
Sidewalks North Sarasota |
Under
construction. |
|
Desoto
Road/Turtle Ave. |
Design
is underway. |
|
Beneva
Road/Fire Station #5 |
Design
is underway. |
|
ATMS |
Phase
1: Construction underway. Phase 2: Construction award in
Dec 2011. |
|
Gulf
Gate/Beneva Rd Intersection |
Under
construction. |
|
Signals
Intersections |
Various
projects under design. See below. |
|
Area K
Resurfacing |
Complete |
|
Road
Resurfacing- Surtax 3 |
All the
ESP resurfacing projects have been substantially
completed. See below for additional projects.
|
|
Area K
& D Resurfacing |
|
|
12A HMA
Resurfacing |
|
|
12B HMA
Resurfacing |
|
|
12C HMA
Resurfacing |
|
|
Verna
Rd Cold in Place |
|
|
Area D
Resurfacing |
complete |
|
Sidewalk Program |
Blackburn sidewalk under design. |
|
Siesta
Bridge Repairs |
|
|
Sarasota Golf Club Blvd. Bridge Repair |
|
|
Brookside Drive, Proctor Road, Lokai Place Bridge
Repairs |
|
|
Central
Ave. & Myrtle St. Bridges |
Complete |
|
Lockwood Ridge Bridge |
Completed |
|
Raymond
Rd Bridge |
Complete |
|
Blackburn Point Bridge |
Complete |
|
Bridge
R&R- Surtax 3 |
various
projects. |
|
Honore
(Pinebrook) |
LFA
with FDOT was approved by the Board on Oct. 13, 2009.
Funding has been transferred to FDOT. |
|
Honore
(Clark to Proctor) |
Ashton/Honore
roundabout design underway. |
|
Bus
Rapid Transit |
Awaiting approval of Project Mgmt Plan and Grant Funding
approval. BCC discussion occurred 10/25/11. BCC
requested follow up workshops Jan 2012. First workshop
occurred on 12/5/11. Second workshop anticipated on
1/27/12. |
|
Upgrade
800MHZ |
New |