|
Project Name |
Status Indicator |
| 17th Street BMX
Renovation |
In planning |
|
Alligator Creek STW Quality |
Design
under way (Watermark) with scheduled completion in March
2010. |
| Baywalk at Ken Thompson
Park |
Partial construction
underway with Ram Marine. Unit Price Contract Work
assignment to be issued in November 2009 for remaining
design and construction. Construction scheduled to be
complete in March 2010 |
| Beach
Access Improvements / Shoreline Access Phase I |
Design
for Beach Access 12 underway (ECE) with scheduled
completion in December 2009. Wharf/Vamo Rd conceptual
design completed (Wilson Miller). Final design underway
(WilsonMiller) with expected completion in December
2009. |
| Bee Ridge Extension |
|
| Ben
Franklin Drive Trail |
Design
underway (PBS&J) with scheduled completion in January
2010. Currently permitting with City of Sarasota.
Construction to be completed through unit price
contracts (Derr and Coastal Construction), Construction
scheduled to be complete in April 2011 |
| Benderson Park
|
Developer to complete
concept plan. Concept plan anticipated to be brought
before the BCC in December 2009. Call for Professional
Services anticipated to be advertised in February 2010 |
|
Blackburn Point Bridge |
Repair
work has been complete. Bridge was opened to vehicular
traffic on June 18, 2009 |
| Blackburn Point Park
Addition |
|
| Blind
Pass Beach Restrooms |
Specific Authorization to CPH for $207,250 approved on
Nov. 18, 2008. Design completion anticipated in December
2009 |
| Boardwalk Replacements -
Alligator Creek (design,constr) |
Unit Price Contract Work
assignment to be issued in December 2009 for design and
construction. Construction scheduled to be complete in
April 2010 |
|
Boardwalk Replacements - Brohard (const.) |
Permitting underway with PBS&J. Construction via Coastal
Facilities unit price contract. Construction scheduled
to be complete in December 2009 |
| Boardwalk Replacements -
Caspersen Beach (design,constr) |
Design and permitting
underway (CTC). Construction via Coastal Facilities unit
price contract. Construction scheduled to be complete in
March 2011 |
|
Boardwalk Replacements - Chauncey (const.) |
Permitting underway with PBS&J. Construction via Coastal
Facilities unit price contract. Construction scheduled
to be complete in December 2009 |
| Boardwalk Replacements -
Lemon Bay (design,constr) |
Unit Price Contract Work
assignment to be issued in December 2009 for design and
construction. Construction scheduled to be complete in
July 2010 |
| Bridge
R&R- Surtax 3 |
See
below |
| Brother Geneen Way
Culvert |
|
|
Caspersen Beach Restrooms |
BCC
approval of Totems contract in the amount of $277,595
for design, permitting and construction administration
on March 17, 2009. Design completion anticipated in
December 2009. |
| Central Ave & Myrtle St
Bridges |
100 percent plans
received. Easements being acquired. Scheduled to
advertise in Nov. 9 |
|
Central Wastewater Collection System Extension |
Call
for Professional Services for feasibility study will
advertise in November 2009 |
| Dona Bay Hydrology Mgmt. |
Design under way (KHA)
with scheduled completion in August 2010 |
| Elsie
Quirk Remodel |
Under
protest by Boran Craig Barber Engel Construction. Ley
denial letter mailed Nov. 16, 2009 |
| Fruitville Park Athletic
Field |
Bids opened Sept. 30,
2009. Bid under protest |
|
Fruitville Rd Coburn Ssta Ctr |
Construction contract for phase 1 from Debrecen to east
of Tatum was awarded on July 21; phase 1 construction
duration is eight months. Phase 2 construction from East
of Tatum to Coburn Road was awarded on Sept. 8.
|
| Gulf Gate Library |
Neighborhood meetings
ongoing to gather public input |
|
History Museum/BCC Challenge G |
Determining scope needs. Negotiating with Totems for
preliminary study |
| Honore Bee Ridge to
Fruitville |
The contract for final
design and construction was awarded on July 21, 2009.
The bridge construction is scheduled to start the week
of Nov. 2. Substantial completion by February 2011.
|
| Honore
(Pinebrook) |
LFA
with FDOT was approved by the Board on Oct. 13, 2009.
Funding has been transferred to FDOT |
| Library Technology
Surtax III |
Contract for AMH systems
is anticipated to be approved by the BCC in October. The
project manager for the AMH portion is Darlene Frazee. |
| Lime
Lake Neighborhood Park |
Lime
Lake design (KHA) underway |
| Lockwood Ridge Bridge |
100 percent plans
received. Advertised Oct. 21. Bid opening scheduled for
Nov. 25 |
|
Manasota Beach Restrooms |
BCC
approval of Totems contract in the amount of $258,800
for design, permitting and construction administration
on March 17, 2009. Design completion anticipated
December 2009. |
| Neighborhood Improvement
Mother Account |
|
| New
Englewood Facility Design |
PSRC
held on July 27, 2009. Fleishman-Garcia was the selected
firm. BCC determined that property to be acquired prior
to any expenditures. |
| Nokomis Beach
Improvements |
Work assignment issued
to Greg Hall Architects for $52,015. Bid opening
scheduled for Nov. 18, 2009 |
| N.
County Sports Complex |
In
planning |
| North Jetty Bch Park RR/Conce |
BCC approval of CPH
contract in the amount of $214,643 for design,
permitting and construction administration. Construction
to begin in April 2011 when funding is expected to be
available. |
| North
Port Health & Family Ser |
Rebidding due to grant requirements and funding issues.
Anticipate advertising in December 2009. |
| Parks & Recreation
Natural Areas |
|
|
Phillippi Creek STW Quality |
Call
for design engineering services to be issued in November
2009. FDEP Grant executed by BOCC on Sept 8, 2009 |
| Raymond Rd Bridge |
100 percent plans
received. Easements are being acquired. Scheduled to
advertise in Nov. 9 |
| Red
Bug Slough Preserve |
Design
(KHA) underway |
| Red Bug Slough
Restoration |
Design underway (PBS&J)
with scheduled completion in April 2010 |
| Road
Resurfacing- Surtax 3 |
All
the resurfacing projects have been substantially
completed |
| Sediment Abatement &
Stabiliz |
Design for both Roberts
and Lemon Bay under way (Progressive Water) with
scheduled completion in July 2010 |
| Selby
Library Remodel, Phase 1 & 2 |
Purchase Order issued to Totems for $146,295. Design
completion anticipated in January 2010. |
| Sheriff's Modem
Replacement |
|
|
Sheriff's Trunked radio |
|
| Sidewalks Bee
Ridge/Wilkinson |
Final completion
certification in progress |
|
Sidewalks Gulf Gate |
Construction contract was awarded June 9, 2009.
Construction is underway, Substantial completion by the
end of December 2009. |
| Sidewalks North Sarasota |
SWFWMD permit has been
approved. ROW acquisition currently in progress.
Necessity of Resolution to the Board on Dec. 8, 2009.
The project is scheduled to advertise in February 2010 |
|
Sidewalks PCSSRP Area D |
Sidewalk construction started April 27, 2009.
Construction ends April 2010. |
| Siesta Beach
Improvements (design) |
Negotiating scope and
fee with Kimley-Horn. Anticipate BCC award in January
2010. |
|
Signals Intersections |
|
| Sleeping Turtles
Preserve (Ligon) |
Issued work assignment
to King Engineering for 94,141. Design completion delay
due to S&D sidewalk issue |
| Snook
Haven Restroom |
Utility easement acquisition underway |
| South Lido Beach
Restrooms |
Work assignment issued
to Totems for $99,707. Design completion expected in
March 2010. Construction to begin in April 2011 when
funding is expected to be available. |
| S.
Lido Trails |
Unit
Price Contract Work assignment to be issued in November
2009 for design and construction. Construction to be
complete in May 2010 |
| Spoil Island Restoration |
$1.1MM surtax money
retained in program for FY-10 budget. Palmer Point
Restoration construction expected to bid in Fall 2009. |
| Street
Tree - Tree Canopy Program |
Various checkbook projects completed with ongoing
establishment periods (Oxford Drive, Palm Terrace, Oak
Terrace, Kensignton Park), under construction (East
Venice), and in design (Fruitville East, Jacaranda
Roundabout, North Cattlemen, Fruitville-Cob-Deb, Honore,
Gulf Gate, Beneva, Old Miakka & Honore 5). Design and
construction authorizations continue through existing
continuing services contracts and annual agreements |
| Transit Maintenance
Facility |
|
|
Transit Stop Improvements |
100
percent plans received. Using Unit Price contract,
construction starts early November 2009. Two additional
design work assignments for PBS&J and HDR currently
being processed |
| Tuscano Park |
In planning |
| Turtle
Beach Renovations |
Call
for design services advertised Nov. 11, 2009. |
| Urfer Family Park (f.k.a.
Honore Trail Park) |
Dedication held on Nov.
14, 2009. Construction completion of Wilson House
expected in July 2010 |
| Water
Service Program to Support the Wastewater Collection
System Extension |
Call
for Professional Services for feasibility study will
advertise in November 2009 |